Town Branch Commons Trail in the home stretch

Town Branch Commons Trail is quickly moving toward completion this fall.

“We started in March 2020 and we’re 90% complete … ahead of schedule,” Mayor Linda Gorton.

Originally, the trail was expected to be complete at the end of the year.

“The next few months will be really exciting as we put on the finishing touches,” Gorton said. “Town Branch Commons Trail is going to be a place to get outdoors and enjoy family fun, art and exercise. And it will offer new opportunities for business, as it invites people to come downtown.”

Remaining construction projects include:

  • Final plaza near the Central Bank Center, which will be completed in conjunction with the convention center’s construction. Central Bank Center is set to hold grand opening ceremonies in April.
  • Final paving and striping of Vine Street, between Quality Street and East Main Street. 
  • Reconfiguration of the Old Vine Street intersection at Vine Street.
  • Completion of the trail along Midland Avenue and East Vine Street
  • Construction of two recirculating water features along Midland Avenue.
  • Landscaping and installation of amenities (signage, bike racks, trash cans, etc.).

 

Several of these projects will affect motorists traveling in the area in the next few weeks. There will be alternating lane closures, but through traffic will be maintained in the area at all times:

  • The left-hand lane of Vine Street will be reopened between Quality Street and East Main Street, and the right-hand lane of Vine Street will be closed to traffic to accommodate work on the south side of Vine.
  • The state will complete roadway repair work on Vine Street, between Quality and Rose streets.
  • There will be continued utility work at the intersection of Vine Street and Rose Street.
  • A new traffic signal will be activated at the Short St and Midland intersection this spring.
  • In May, final milling, paving, and striping is scheduled on Vine Street, between Quality Street and East Main Street, completing all paving for the project.
  • Landscaping and tree plantings will continue in late March and April along Vine Street and Midland Avenue.

 

Town Branch Commons Trail will be the hub of a city-wide trails system, connecting our downtown parks and two major trails. Town Branch Commons will connect to Legacy Trail and Town Branch Trail, creating a 5.5 mile loop on the north side of downtown, and providing access to 22 continuous miles of dedicated walking, jogging, and cycling trails connecting the city center to the countryside.

The Commons connects diverse neighborhoods as it follows the historic path of Town Branch, Lexington’s original water source.

Pace Contracting is building the trail.

###

You may also like...

Link to City announces “Be the Change” scholarship winners
Apr. 23, 2024 12:07 pm

City announces “Be the Change” scholarship winners

Bryan Station seniors Michelle Moore and Aline Sandoval Cano are the recipients of the 2024 “Be the Change” scholarships.
Link to Free paper shred for Lexington residents
Apr. 23, 2024 11:08 am

Free paper shred for Lexington residents

Lexington will host a free paper shred event on Saturday, April 27 from 9 a.m. to 2 p.m. at 1631 Old Frankfort Pike.

Link to Council launches public input website
Apr. 22, 2024 11:17 am

Council launches public input website

Mayor Linda Gorton today joined Urban County Councilmembers to announce the Council’s new public input website, “Engage Lexington.”