Wolf Run sanitary sewer project

The Wolf Run Sanitary Sewer project involves replacing two sanitary sewer trunk lines, Wolf Run Trunk D and Wolf Run Trunk E. This project runs through the Beacon Hill and Wolf Run park areas. Currently, there is construction near the creek crossing at Appomattox Rd. Half of the manholes and over 60% of the pipe has been laid for this project. 

As of early March 2022, Gardenside Park is closed to the public for safety reasons during construction. Park reopening is anticipated by the end of April. 

 

Where is the sanitary sewer line?

map of sanitary sewer line running through Wolf Run Park

map of sanitary sewer line running through Wolf Run Park